FCDA Road Dualization: TCN Restores Full Bulk Power to Apo Transmission Substation
This post has already been read 271 times!
The Transmission Company of Nigeria (TCN) has announced the restoration of full bulk power to its 132/33kV Apo Transmission Substation, effective Thursday, January 23, 2025.
This restoration follows the successful relocation of eight 132kV and 33kV towers along the Kukwaba/Apo 132kV line (Southern Expressway route), necessitated by the Federal Capital Development Agency’s (FCDA) road dualization project along the Apo axis.
The two-week relocation work, which commenced on Monday, January 6, 2025, involved dismantling, and reconstructing the towers, as well as restringing power cables.
“With the restoration of full bulk power, Abuja DisCo can now provide normal electricity supply from the substation to its customers in the affected areas, ending the previous load rationing.
“TCN appreciates the patience and understanding of the affected electricity consumers during this period”, said Ndidi Mbah,
General Manager (GM), Public Affairs, TCN, in a statement at the weekend.